16 Flack Avenue, Hillsdale
NSW 2036
info@speedylinemarking.com.au
ABN 32 673 397 503
Quote Number | QUO-1105 |
Quote Date | January 17, 2025 |
Total | $60,223.35 |
Hrs/Qty | Service | Rate/Price | Sub Total |
---|---|---|---|
1 | Yellow/black line 300mm wide (2 black sided line at 100mm each / yellow line at 100mm) Approx 1000ml A1 Dulux road master |
$4,000.00 | $4,000.00 |
1 | 131x single letter 2m each A1 Dulux road master |
$9,170.00 | $9,170.00 |
1 | Approx 150m dotted black/yellow at 300mm A1 Dulux road master |
$4,500.00 | $4,500.00 |
1 | 262m2 of black background A1 Dulux road master |
$5,240.00 | $5,240.00 |
1 | EXTRA ITEM ONE: Yellow/black line 300mm wide (2 black sided line at 100mm each / yellow line at 100mm) Approx 1500ml A1 Dulux road master |
$6,000.00 | $6,000.00 |
1 | EXTRA ITEM TWO: 137x single letter 2m each A1 Dulux road master |
$9,590.00 | $9,590.00 |
1 | EXTRA ITEM THREE: Approx 250m dotted black/yellow at 300mm - A1 Dulux road master |
$7,500.00 | $7,500.00 |
1 | EXTRA ITEM FOUR: 280m2 of black background A1 Dulux road master |
$5,600.00 | $5,600.00 |
1 | EXTRA ITEM FIVE: Red line with parallel yellow line - approx 400ml A1 Dulux road master |
$1,600.00 | $1,600.00 |
1 | EXTRA ITEM SIX: 29x Yellow 'stop' lines - approx 3mL x 600mW A1 Dulux road master |
$2,610.00 | $2,610.00 |
4 | EXTRA ITEM SEVEN: Diagonal plane parking A1 Dulux road master |
$400.00 | $1,600.00 |
1 | ESTABLISHMENT FEES:(7x night work 5x workers) All work to be conducted in accordance with Australian standards |
$7,000.00 | $7,000.00 |
Sub Total | $64,410.00 |
Tax | $5,474.85 |
Discount | -$9,661.50 |
Total | $60,223.35 |